Project Implementation Report
Monthly Report – January 2025
(Construction letting dates dependent upon land acquisition completion)
Bunker Road Extension – Keslinger Road to LaFox Road
- Included in the County’s long-range transportation plan since 2004 and identified in the late 1990s as a key improvement to reduce congestion and enhance north/south connectivity.
- The extension incorporates an underpass of the UPRR tracks (constructed during the Metra West Line extension in 2006) and includes a roundabout at Bunker and Keslinger Roads.
- Bids opened in November 2024; construction will continue through the summers of 2025 and 2026.
Dauberman Road/Meredith Road Realignment
- Phase I (PE I) is underway to determine the optimal realignment south of Keslinger Road. Multiple alignments are being evaluated.
Fabyan Parkway (IL 31 to IL 25)
- A Planning and Environmental Linkages (PEL) study completed in 2023 provided feasible design alternatives for intersection improvements at Fabyan and IL 31.
- PE I is in progress to address necessary improvements, including the Fox River Bridge and the Fabyan/IL 25 intersection. Bicycle and pedestrian accommodations will also be considered.
- Project website: Fabyan-IL 31 Intersection.
Fabyan Parkway at Settler’s Hill and Kingsland Drive
- Phase II (PE II) is underway for intersection and roadway improvements, including widening for auxiliary turn lanes and ADA upgrades.
Galligan Road (Binnie Road to Freeman Road)
- PE I is in progress for safety and capacity improvements, including potential roundabouts, pavement widening, drainage enhancements, and future multi-use path construction.
Kirk Road over UPRR, Metra & Tyler Creek
- The existing 18-span bridge will be replaced with three single-span bridges and retaining walls. PE II and ROW acquisition are ongoing.
Longmeadow Parkway Bridge Corridor
- New alignment and bridge construction over the Fox River.
Tree Growing Contract
- Plan preparation is nearly complete, with a construction letting targeted for 2025.
Montgomery Road at Howell Place
- PE I/II is underway for intersection improvements, including widening, permanent signals, ADA enhancements, and reconfiguration of commercial entrances.
Plank Road (Romke Road to Brier Hill Road)
- PE II is in progress for federally funded safety upgrades, including shoulder widening, rumble strips, reflective markers, and ditch grading.
Plank Road (West County Line Road to Engel Road)
- PE I is underway for similar federally funded safety enhancements.
Randall Road at IL 72 Intersection Reconstruction
- PE II is in progress to expand capacity and improve pedestrian safety, targeting an April 25, 2025, IDOT letting.
Randall Road at Big Timber Road Intersection Reconstruction
- PE II is underway for capacity and safety improvements, including a third through lane, reconfigured turn lanes, and a 10-ft multi-use path.
Randall Road at US 20 Interchange Improvements
- A PEL study completed in 2022 addressed increased traffic volumes and access needs. Phase I engineering is now in progress, focusing on a turbine-style interchange.
Randall Road over I-90 Interchange
- Following a 2021 PEL study, PE I is in progress, refining the preferred alternative. Public comments have been incorporated. Project website: Randall Over I-90.
Randall Road at Hopps Road and over CNRR
- PE II and ROW acquisition are underway for intersection realignment and a grade-separated crossing over the CNRR.
Randall Road Multi-Modal Improvements
- PE I is in progress for 9.4 miles of improvements, including off-road shared-use paths, sidewalks, and enhanced pedestrian crossings. Project website: Randall Road Multi-Modal.
Randall Road at Highland Avenue
- PE I is underway to expand Randall Road to three lanes in each direction, with urban cross-section upgrades and pedestrian/bike path additions.
Tyrrell Road (Raymond Road to Mason Road)
- PE I is in progress for modernization and safety improvements, including multi-modal connectivity.
Various Engineering Projects
- Numerous active projects are in various stages of development. For more information, visit KDOT Highway Projects.
- Numerous active projects are in various stages of development. For more information, visit KDOT Highway Projects.