Extension of Dauberman Road
Construction for the Dauberman Road Extension improvement is scheduled to begin the week of May 8th, weather permitting. The work consists of widening, reconstruction, and extending Dauberman Road from US 30 to Granart Road. Single-span bridges will be constructed on Dauberman Road over US 30 and over the Burlington Northern and Santa Fe (BNSF) Railway. The work will consist of earthwork, pavement removal, roadway reconstruction, pavement widening, sidewalk and a multi-use path, storm sewer, landscaping, and bridge construction. The anticipated completion date for the project is November 2024, weather permitting.
The above-mentioned roads will remain open during construction but may need temporary daily lane closures and flaggers at various stages of the construction. Work hours will be Monday through Saturday from 7:00 A.M. to 5:00 P.M. Motorists should expect delays while traveling through the work areas and should add additional time to their commutes.
Source KDOT media release